Notable Projects

Pressure grouting pretreatment of soils in preparation for the installation of a 12’ diameter pedestrian tunnel beneath Union Pacific railroad track.

Martam Construction

Project: Raymond St. Forest Preserve Bike Bath & Pedestrian Tunnel
Location: Elgin IL
Description of Work: Pressure grouting pretreatment of soils in preparation for the installation of a 12’ diameter pedestrian tunnel beneath Union Pacific railroad track. MasterRoc MP 650 Microfine Cement used to immobilize soils.

Des Plaines River coffer dam bedrock floor leaking

IHC Construction

Project: Lockport Lock and Dam Powerhouse, Corps of Engineers/Greater Water Reclamation District of Chicago
Location: Lockport IL
Description of Work: Des Plaines River coffer dam bedrock floor leaking 1,200 GPM water cutoff. Terrathane 24-070 used to perform water cut-off.

Cutoff wall grouting for the purpose of uranium containment.

Weston Solutions

Project: Former Rare Earth Facility Superfund Site Remediation Project
Location: West Chicago, IL
Description of Work: Cutoff wall grouting for the purpose of uranium containment. MasterRoc MP 650 Microfine Cement and Strata-tech ST-504 gel solution grout used to perform sealing.

Soil densification, concrete raising, and void filling

Eastlake Management

Project: United States Social Security Administration Office
Location: Chicago, IL
Description of Work: Soil densification, concrete raising, and void filling. Terrathane 24-070 and 24-003 were used on this project.

Soil densification using high-density polyurethane to stabilize urban fill.

De James Builders, Inc

Project: Walgreens – US Flag Ship Store
Location: Chicago, IL
Description of Work: Soil densification using high-density polyurethane to stabilize urban fill. Terrathane 24-030 was used on this project.

Compaction grouting to provide soil improvement to inhibit soil erosion from water migration, void filing, and create water cut off.

Four Points RV Resorts

Project: Earthen Dam Grouting Pine Lakes RV Resort
Location: Pittsfield, IL
Description of Work: Compaction grouting to provide soil improvement to inhibit soil erosion from water migration, void filing, and create water cut off. Terrathane 24-003 was used on this project.

Utility Connection Pit Water Cut-Off

L.J. Keefe – Commonwealth Eddision

Project: Utility Connection Pit Water Cut-Off
Location: Vernon Hills, IL
Description of Work: Compaction grouting and void filling to provide soil improvement by displacement to sufficiently inhibit soil erosion, fill underlying voids, seal sheet pile joints, and create water cut off. Terrathane 24-003 and 24-039 were used on this project.

O’Hare Airport Utility Connection Pit Water Cut-Off

JayDee Contractors Inc.

Project: O’Hare Airport Utility Connection Pit Water Cut-Off
Location: O’Hare Airport, IL
Description of Work: Compaction grouting to provide soil improvement, water cut off for fifteen foot diameter tunnel connections beneath airport runways. Terrathane 24-003 was used on this project.

Soil stabilization Northwestern University Ryan Field Football Stadium

Thatcher Foundations Inc.

Project: Northwestern University Ryan Field Football Stadium
Location Evanston, IL
Description of Work: Soil stabilization around soil nails and sheeting to prevent soil loss and leaching water. Terrathane 24-039 was used on this project.

Communication Vault Water Cut-Off

Pearce Services & AT&T

Project: Communication Vault Water Cut-Off
Location Los Angeles, CA
Description of Work: Permeation grouting to inhibit water infiltration into telecommunications vault. Strata-tech ST-504 was used on this project.

Thatcher Foundations, Inc.

Project: MGNWC Nagle Avenue Pump Station
Location Morton Grove, IL
Description of Work: Trench grouting water cutoff around twin 48" diameter water lines. Granular bedding materials below grade and adjacent to the pipelines was pumped to fill voids using a high density , rapidly expanding geo polymer foam.

For Pipeline re-Alignment

American Trenchless Technologies

Project: For Pipeline Alignment
Location Chicago, IL
Description of Work: Restaurant 6’’ sanitary line broke 7 feet below-grade in front of the building located under a sidewalk near several utility lines and a traffic signal. Lincoln performed soil extraction to lower the pipe section back into alignment for re-lining without excavation. Lincoln’s patented Soil Extraction Device was used on this project.